Before Trouble Strikes: Part I

July 12, 2001
By Elizabeth M. Ferrarini




In 1992 Hurricane Andrew put 39 major data centers out of commission. And in 1993 the World Trade Center bombing caused 21 data centers to shut down. While you don't like to think about it, every organization, regardless of its size, runs the risk of a major systems outage, such as a tornado demolishing a data center or a building fire destroying the facility and everything in it. A study by the University of Texas found that 85 percent of businesses depend totally or heavily on information technology systems to stay in business, and that a loss of those systems would cost businesses up to 40 percent of their daily revenues.

Disaster can strike at any time. In fact, there are more than 35 types of disasters, ranging from the most common, such as power outages, to the most catastrophic, such as earthquakes. In essence, a disaster includes any type of interruption of service that results from some force beyond the organization's control. Disaster recovery provides systematic procedures for how to react to and how to recover from that ominous external or internal force. Disaster recovery planning, which complements business continuity and contingency planning, ensures the ability of the organization to function effectively if an unforeseen event severely disrupted normal operations.

The following checklist will help the key individuals in your organization prepare a disaster recovery plan. The objective is to restore all critical business functions, rather than just such disparate functions as the data center.

Gather Information

Organize the Project
A successful initiative of this magnitude requires support from senior management associated with the organization, a dedicated disaster recovery team whose members have knowledge of critical business systems, and a well thought out planning and testing strategy.

Senior executives responsible for disaster recovery planning will perform the first two steps. The disaster recovery coordinator, working with the appropriate team leaders, should perform steps 3 to 7.

  1. Determine which senior executive(s) will have overall responsibility for disaster recovery.
  2. Have this executive appoint disaster recovery coordinator.
  3. Appoint a disaster recovery team leader for each operational unit, such as server backup or telephone system.
  4. Convene disaster recovery planning team and sub-teams as appropriate.
  5. Working with senior executives responsible for disaster recovery, the disaster recovery coordinator should identify the following:
    • Scope -- the areas to be covered by the disaster recovery plan
    • Objectives -- what is worked towards and what is the course of action that the disaster recovery team intends to follow
    • Assumptions -- what is being taken for granted or accepted as true without proof?
  6. Set project timetable and draft project plan, including assignment of task responsibilities.
  7. Obtain senior management's approval for scope, assumptions, and project plan.

Conduct Business Impact Analysis
The disaster recovery planning team should perform this step to identify which business departments, functions, or systems are most vulnerable to potential threats, what are the potential types of threat, and what effect would each identified potential threat have on each of the vulnerable areas within the organization.

  1. Identify functions, processes, and systems.
  2. Interview information systems support personnel.
  3. Interview business unit personnel.
  4. Analyze results to determine critical systems, applications, and business processes.
  5. Prepare impact analysis on interruption on critical systems.

Conduct Risk Assessment
The disaster recovery planning team should work with the organization's technical and security person to determine the probability of each functional business units' critical systems becoming severely disrupted and to document the amount of acceptable risk the business unit can tolerate. For each critical system, provide the following information:

  1. Review physical security, i.e. secure office, building access off hours, etc.
  2. Review backup systems and data security.
  3. Review policies on personnel termination and transfer.
  4. Identify systems supporting mission critical functions.
  5. Identify vulnerabilities, such as physical attacks, or acts of God, such as floods.
  6. Assess probability of system failure or disruption.
  7. Prepare risk and security analysis.

Develop Strategic Outline for Recovery
The steps outlined here provide all of the components necessary to perform a recovery. These steps will help pull together information about the operations of all systems, especially those owned or managed by non-technical managers with help from technical support personnel. Steps one through four mainly apply to functional business units that manage technology systems to process critical functions. The disaster planning recovery team and the functional business unit may wish to appoint other appropriate individuals to perform subsequent tasks.

  1. Assemble groups as appropriate for the following:
    • Hardware and operating systems
    • Communications
    • Applications
    • Facilities
    • Other critical functions and business processes as identified in
    • the Business Impact Analysis step.
  2. For each system/process above quantify the following processing requirements.
    • Light, normal, and heavy processing days
    • Transaction volumes
    • Dollar volume, if any
    • Estimated process time
    • Allowable delays (days, hours, minutes, etc.)
  3. Detail all the steps in your workflow for each critical business functions. (For example, for payroll processing include each step that must be complete and the order in which to complete them.
  4. Identify systems and applications.
    • Component name and technical identification if any
    • Type (online, batch process, script)
    • Frequency
    • Run time
    • Allowable delay (days, hours, minutes, etc.)
  5. Identify all vital records.
    • Name and description
    • Type (backup, original, master, history)
    • Where are they stored?
    • Source of item or record
    • Can the record be easily replaced by another source?
    • Backup and backup generation frequency
    • Number of backup generations available onsite and off-site
    • Location of backups
    • Media key, retention period, rotation cycle
    • Who is authorized to retrieve the backups?
  6. Identify if a severe disruption occurred what would be the minimum requirements or replacement of the critical function during the disruption.
    • Type (server hardware, software, research materials, etc.
    • Item name and description
    • Quantity required
    • Location of inventory, alternative, or off-site storage
    • Vendor/supplier
  7. Identify if alternative methods of process either exist or could be developed, quantifying on processing (include manual processes).
  8. Identify person(s) who support the system or the application.
  9. Identify primary person to contact if system or application cannot function as normal.
  10. Identify secondary person to contract if system or application cannot function as normal.
  11. Identify all vendors associated with the system or application.
  12. Document business unit strategy during recovery (conceptually how will the unit function?).
  13. Quantify resources required for recovery by time frame.
  14. Develop and document recovery strategy, including priorities for recovering system/function components, and recovery schedule.

Review On-site and Off-Site Backup and Recovery Procedures
The disaster recovery planning team should perform this task to provide for a current backup of critical program and data that can be used in the even of a disaster. To this end, the disaster recovery planning time can reduce downtime and speed recovery.

  1. Review current records (operating systems, code).
  2. Review current off-site storage facility or arrange for one.
  3. Review backup and off-site backup storage policy or create one.
  4. Present to functional business unit leader for approval.

Select Alternate Facility
The disaster recovery should perform the task of looking for a location, other than the normal facility, used to process data and or conduct business, in the event of a disaster.

  1. Determine resource requirements.
  2. Assess platform uniqueness of unit systems (Macintosh, IBM, Oracle, etc.).
  3. Identify alternative facilities.
  4. Review cost/benefit.
  5. Evaluate and make recommendation.
  6. Present to business unit leader for approval.
  7. Make selection.

In part 2, we will cover Plan Development, Testing, and Ongoing Maintenance for your disaster recover plan.

1
IT Offers







JupiterOnlineMedia

internet.comearthweb.comDevx.commediabistro.comGraphics.com

Search:

Jupitermedia Corporation has two divisions: Jupiterimages and JupiterOnlineMedia

Jupitermedia Corporate Info


Legal Notices, Licensing, Reprints, & Permissions, Privacy Policy.

Advertise | Newsletters | Tech Jobs | Shopping | E-mail Offers

Solutions
Whitepapers and eBooks
IBM Whitepaper: Innovative Collaboration to Advance Your Business
Internet.com eBook: Real Life Rails
Avaya Article: Call Control XML - Powerful, Standards-Based Call Control
Tripwire Whitepaper: Seven Practical Steps to Mitigate Virtualization Security Risks
Internet.com eBook: The Pros and Cons of Outsourcing
Go Parallel Article: Scalable Parallelism with Intel(R) Threading Building Blocks
Internet.com eBook: Best Practices for Developing a Web Site
IBM CXO Whitepaper: The 2008 Global CEO Study "The Enterprise of the Future"
Avaya Article: Call Control XML in Action - A CCXML Auto Attendant
Go Parallel Article: James Reinders on the Intel Parallel Studio Beta Program
IBM CXO Whitepaper: Unlocking the DNA of the Adaptable Workforce--The Global Human Capital Study 2008
Adobe Acrobat Connect Pro: Web Conferencing and eLearning Whitepapers
Go Parallel Article: Getting Started with TBB on Windows
HP eBook: Storage Networking , Part 1
MORE WHITEPAPERS, EBOOKS, AND ARTICLES
Webcasts
Go Parallel Video: Intel(R) Threading Building Blocks: A New Method for Threading in C++
HP Video: Is Your Data Center Ready for a Real World Disaster?
Microsoft Partner Portal Video: Microsoft Gold Certified Partners Build Successful Practices
HP On Demand Webcast: Virtualization in Action
Go Parallel Video: Performance and Threading Tools for Game Developers
Rackspace Hosting Center: Customer Videos
Intel vPro Developer Virtual Bootcamp
HP Disaster-Proof Solutions eSeminar
HP On Demand Webcast: Discover the Benefits of Virtualization
MORE WEBCASTS, PODCASTS, AND VIDEOS
Downloads and eKits
Microsoft Download: Silverlight 2 Software Development Kit Beta 2
30-Day Trial: SPAMfighter Exchange Module
Red Gate Download: SQL Toolbelt
Iron Speed Designer Application Generator
Microsoft Download: Silverlight 2 Beta 2 Runtime
MORE DOWNLOADS, EKITS, AND FREE TRIALS
Tutorials and Demos
IBM IT Innovation Article: Green Servers Provide a Competitive Advantage
Microsoft Article: Expression Web 2 for PHP Developers--Simplify Your PHP Applications
Featured Algorithm: Intel Threading Building Blocks - parallel_reduce
MORE TUTORIALS, DEMOS AND STEP-BY-STEP GUIDES